The Challenges

AMA appointed MaxBuild to undertake the re-lining of the 189 metre long Rosedale culvert.

The existing culvert was showing significant signs of deterioration and the consultant’s methodology for repair was to install a reinforced concrete lining.

MaxBuild undertook all the site activities including diversion of the water flow, installation of steel reinforcement before shotcreting of 145m3 of concrete.

The project was completed on time and budget.

Project Description

Client:Auckland Motorway Alliance
Location:Rosedale, Albany
Year Completed:2015